Thermal power plants are a crucial part of the Brazilian electrical system, and with the proposed flexibility in their operation, significant savings for energy consumers can be envisioned.

This article will explore how this change, which involves the operability of three power plants, could generate estimated savings of between R$1,7 billion and R$3,2 billion, while also providing greater efficiency and responsiveness of the electrical system to variations in demand.

The analysis by the Chamber of Electric Energy Commercialization (CCEE) and the consulting firm PSR will be discussed, as well as its impact on reducing charges and costs for consumers.

Potential Savings for Consumers

Easier operation of thermal power plants could generate estimated savings of between R$1,7 billion and R$3,2 billion for consumers in the regulated market, reducing charges that currently put pressure on electricity bills.

In practice, the change would allow the National Electric System Operator to activate these power plants only when there is a real need, which improves energy dispatch and avoids unnecessary costs passed on to tariffs.

Furthermore, the proposal discussed based on analyses by CCEE and the consulting firm PSR indicates significant gains in system efficiency because it adjusts supply to demand variations more precisely.

Key gains

  • Reduced use of thermal power plants when cheaper energy is available.
  • Reduction of charges paid by consumers in the tariff.
  • Greater operational efficiency in meeting electricity demand.

Flexibility in Power Plant Operation

The increased flexibility in operating thermal power plants represents a significant innovation in the electricity sector, allowing them to adjust more efficiently to fluctuations in energy demand.

With the implementation of this mechanism, the dispatch of power plants will be carried out in a more dynamic way, activating them only when truly necessary and thus contributing to a more economical management of energy resources.

This adaptability of the electrical system not only improves its efficiency, but also provides a significant reduction in costs for consumers.

Three Power Plants Covered

The three power plants included in the proposal are UTE Maranhão III , in Maranhão; UTE MC2 Nova Venécia 2 , in Espírito Santo; and UTE Azulão II and UTE Azulão IV , in Amazonas, which are part of the package because they together have approximately 1,2 GW of installed capacity.

They were chosen because they are located in strategic regions to reinforce supply security and respond more efficiently to variations in demand.

Thus, with this flexibility, the ONS (National System Operator) can activate these thermal power plants only when there is a real need, reducing contractual inflexibilities and, consequently, charges paid by consumers in the regulated market.

Evaluation by CCEE and PSR Consulting

Assessments by CCEE and the consulting firm PSR indicate that allowing more flexibility in the activation of thermoelectric plants could reduce costs and alleviate tariffs in the regulated market, with estimated savings between R$ 1,7 billion and R$ 3,2 billion.

According to studies, the change improves operational coordination because it allows the ONS (National System Operator) to activate power plants only when there is a real need, avoiding unnecessary generation during periods of lower demand.

Furthermore, the proposal increases the system's efficiency by enhancing its response to load variations, which reduces costs associated with rigid plant operation.

CCEE argues that this design reduces cost increases for consumers, while PSR highlights economic gains by aligning energy supply and demand.

Thus, contractual and operational flexibility emerges as a measure to contain sectoral expenses and strengthen the management of the electricity system.

ONS Efficiency and Implementation Schedule

The increased flexibility in activating thermoelectric power plants tends to give the ONS (National System Operator) more precision in managing electricity operations, because it reduces the premature use of expensive generation and allows the plants to be switched on only when demand truly requires additional support.

With this, the operator gains a more refined tool to handle load variations, meet consumption peaks, and respond to system events with less operational waste.

Furthermore, the measure improves the coordination between thermal dispatch, water availability, and energy security needs, making management more efficient and less dependent on automatic activations outside of the best technical moment.

In practice, the ONS ( National System Operator) will have greater freedom to choose when to activate each unit, adjusting operations based on systemic needs criteria and not just rigid triggers.

This increases efficiency because it avoids unnecessary costs, reduces charges passed on to consumers, and improves operational predictability.

July 2027 is the projected date for the proposal to come into effect, a period necessary for regulation, operational adaptation, and integration of procedures between agents and the operator.

Therefore, the ONS (National System Operator) should reach this stage with greater responsiveness and more control over the use of thermal power plants.

Thermal power plants will play an essential role in improving the overall efficiency of the electrical system.

With implementation scheduled for July 2027, the increased flexibility in activation is expected to not only reduce costs but also optimize the operation of the National Electric System Operator (ONS).